// OUR REFERENCES

They trust us

The group's inflatable devices are deployed on the sites of France's leading construction majors.

// GROUP CLIENTS

Leading construction majors trust us

Vinci
Bouygues
Eiffage
Spie Batignolles
NGE
// CASE STUDY
Spie Batignolles

Labeuvrière WtE plant (France)

Waste-to-Energy plant: 100,000 t/year processed, supplying energy to the city of Béthune and its industries. €35M civil works budget, over 300 people mobilised.

// EQUIPMENT USED

Formwork cushion + stop-end

Rebar and wall formwork, Labeuvriere WtE site
Slab and formwork in place, Labeuvriere WtE site
General view of the Labeuvriere WtE site
// RESULTS OVER 5 MONTHS

Measured gains

10 days
saved on schedule (3 d/month)
15-20%
savings on wall labour budget
0
scabbling at construction joints
6 skips
of wood waste avoided (> 48 m³)
// TESTIMONIAL

"This solution let me approach my role as site manager differently: significant labour savings, faster formwork rotations, simpler implementation for the crews, and construction joints done properly."

Louis

SITE_MANAGER / SPIE_BATIGNOLLES

Your site has its own constraints?